Inspired by a practical tiling video. This guide is based on the YouTube video "How to tile over tiles", which does a good job of showing the checks and prep work that make the difference between tiles that stay put and tiles that do not. The section on keying and priming is well worth a watch.
1. Check whether the existing tiles are solid
Tap across the existing tiles with a coin or the handle of a screwdriver. A hollow sound means the tile has lifted from the substrate behind it. Any tile that moves, flexes, or sounds hollow needs to come off before you go over it.
If more than a few tiles are hollow, it is probably quicker to strip the wall back and start fresh. Tiling over a surface that is already failing just delays the problem.
2. Check the depth - doors, frames, and fittings
Adding a second layer of tiles adds around 8 to 12mm to the wall or floor surface. Around a door frame, that can mean the architrave no longer sits flat, or a door stops clearing the floor. Measure and think it through before you commit.
Floor-to-ceiling tiling in a shower can also create issues where the tiles meet skirting or bath panels. It depends, so plan the whole job before you start mixing adhesive.
3. Clean and key the existing tiles
Clean the existing tiles thoroughly - grease, soap scum, and limescale all stop adhesive gripping properly. Sugar soap works well, followed by a thorough rinse.
Once clean, key the surface by rubbing over it with 60-grit abrasive paper or a diamond sanding pad. You are not trying to remove the glaze - just take the shine off so the adhesive has something to bite into. Some tilers also apply a tile adhesion primer at this stage, which helps on glazed surfaces.
4. Apply the tile adhesive
Use a flexible tile adhesive rated for tiling over tiles - check the manufacturer's guidance. Standard grey or white adhesive works well for most wall tiles. For floors, use a floor-grade adhesive that will cope with movement underfoot.
Apply with a notched trowel, combing the adhesive in one direction. Work in manageable sections so it does not skin over before the tiles go on.
5. Set out and lay the new tiles
Find your centre lines and work outwards from there, the same as any tiling job. The existing grout lines from the layer below will not necessarily line up with your new tiles - use tile spacers and work to your new layout, not the old one.
Press each tile firmly into the adhesive with a slight twisting motion, then check with a spirit level as you go. Catching a problem early is straightforward. Catching it once a whole wall is done is not.
6. Grout and seal
Leave the adhesive to set fully - usually 24 hours - before grouting. Apply grout with a rubber float, working it into the joints at an angle, then wipe off the excess with a damp sponge. Clean up any haze with a dry cloth before it hardens.
Once the grout has cured, run a bead of sanitary silicone in any corners, along the bath edge, or at the floor junction. Silicone allows movement where grout would eventually crack.
When to call a handyman
If the existing tiles are in a poor state, the wall is not flat, or the depth issue is going to cause problems with doorframes or fittings, it is worth getting Richard in to have a look. Sometimes a strip-and-retile is the right answer, and sometimes tiling over works fine - it just depends on what is there.
Need tiling done properly?
The Sandwich Handyman covers wall tiling, floor tiling, grouting, and other home repairs in Sandwich and the surrounding East Kent area.
Contact Richard