A paving slab that rocks underfoot or sits noticeably lower than its neighbours is a tripping hazard and usually not too difficult to fix. In most cases you can lift it, re-bed it, and re-point in a morning - provided the slab itself comes up in one piece.

Inspired by a helpful YouTube guide. This walk-through is based on a UK video covering how to lift, re-bed, and re-point a patio using existing slabs. It is a good watch before you start, particularly for the bedding mix and pointing stages. Worth ten minutes of your time before you get the crowbar out.

1. Find out which slabs actually need attention

Walk the patio slowly and press on each slab with your foot. Any that rock, bounce slightly, or sound hollow when you tap them are bedded poorly and will need lifting. Mark them with chalk so you do not forget.

Check the pointing around each problem slab too. If it is crumbling away right to the base, the whole joint needs clearing before you re-lay. Good pointing around a loose slab is not enough to hold it - the bedding has to be right.

2. Clear the pointing around the slab

Use a cold chisel and club hammer or a grout rake to work out the pointing from all four sides of the slab. Try to clear it right down to the bedding so the slab can lift cleanly without snagging on hardened mortar.

Take your time here. Rushing the pointing removal is how slabs get chipped or cracked as you try to lever them. Five minutes with a chisel is better than a cracked slab and a trip to the builders' merchant.

3. Lever the slab up carefully

Slide a wide bolster chisel or a flat bar under one edge and lift gently. Work progressively around all four sides rather than forcing it up from one point. If the slab is large or heavy, get someone to help - awkward lifting on uneven ground is an easy way to hurt your back.

If the slab is well bonded to the bed and will not budge, try a few gentle taps with a rubber mallet around the perimeter first to break the suction. Do not force it. Sometimes a slab just comes up well, and sometimes it does not.

4. Check what is underneath

Once the slab is up, have a look at the bedding. It could be a sand-and-cement mortar bed, sharp sand, or even compacted soil under older patios. If the bed has collapsed, washed out, or settled unevenly, you need to address that before putting the slab back.

Scrape out any crumbling or loose material from the base. If the bedding has just settled unevenly but is otherwise solid, you may be able to pack it up with a little dry mortar mix and re-set the slab directly.

5. Prepare a fresh bed

For most domestic patios, a semi-dry mortar bed works well. Mix sharp sand and ordinary Portland cement at five parts sand to one part cement, dry or barely damp. Spread it evenly across the excavated area to a depth of about 40 to 50mm and roughly level it off with a straight edge.

Do not use wet, sloppy mortar for paving beds. It is harder to level and the slab can sink before it sets. The semi-dry mix is forgiving and gives you time to adjust.

6. Set the slab back and check for level

Lower the slab back into position and check it sits flush with the surrounding slabs. Use a spirit level or a straight edge across to neighbouring slabs. The slab should sit at the same height with a slight fall away from the house - roughly 1 in 60 is the standard guidance for drainage.

If it sits too high, remove it and scrape out some bed. Too low, add more mix. It is worth taking a bit of time here rather than rushing and re-doing it in six months.

7. Tamp gently into place

Once level, tamp the slab down using a rubber mallet or a timber offcut and club hammer, working around all four sides evenly. This beds the slab into the mortar mix and settles it in position.

Check the level again after tamping. It tends to drop slightly more in the middle when the bedding is a little soft. A few extra tamps in the right place usually fixes it.

8. Leave it to set before walking on it

Stay off the slab for at least 24 hours, ideally 48 if the weather is cold or damp. The mortar bed needs time to begin curing before it can take any load. Put a cane or some tape across the area so nobody steps on it accidentally.

9. Re-point the joints

Once the bedding has cured, brush in kiln-dried sand or point up with a wet mortar mix (3:1 sand to cement) depending on the joint width and your preference. Kiln-dried sand swept in and watered is quicker and works well for smaller gaps. For wider joints or areas that get heavy use, a wet mortar pointing gives a neater, more durable result.

Keep the pointing slightly below the slab surface so water drains away rather than pooling along the joints.

When to call a handyman

If more than a handful of slabs are loose, the whole base may have shifted or the sub-base may have failed. That is a bigger job and usually needs the patio to be lifted and re-laid properly rather than patched one slab at a time. Richard can take a look and give you an honest view of what is worth doing.